For the welds of high-pressure pipes in power plants, in addition to non-destructive testing, should hardness testing also be carried out?

2016-08-28View Original

Thread Content

For the welds of high-pressure pipes in power plants, in addition to non-destructive testing, should hardness testing also be carried out?
Reply #22016-08-28
It is needed. It is generally required that the weld undergo post-weld heat treatment, with a hardness of less than 250HB.
Reply #32016-08-29
Take a look at the standards cited in your design drawings. . A hardness test may be required
Reply #42016-08-29
In accordance with the DL/T438 standard, it is necessary to measure the hardness

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.