Why is the downtime during suspension of hot work class 13 counted as part of the 8-hour period for special-class work?

2023-07-27View Original

Thread Content

Why are the validity periods for special-grade and first-grade hot work permits set at 8 hours? Starting from what time point is this period calculated? Is any time spent during interruptions in the work counted within those 8 hours?
Reply #22023-07-27
Starting from when the task begins, the interruption time is counted within 8 hours.
Reply #32023-07-27
The start time of the task, permitted by the team leader after ticket verification, is taken as the starting point; any interruptions are counted as part of the task duration.
Reply #42023-07-27
Starting from the time signed on the ticket, interruptions are considered within 8 hours.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.