Procedures for the use of pressure pipes and containers in the factory

2018-03-10View Original

Thread Content

I would like to ask everyone for advice regarding the use of pressure pipelines and equipment: 1. For new projects that involve pressure pipelines and pressure vessels, what procedures need to be followed? 2. After commissioning, if some pressure pipelines or pressure vessels need to be modified or added, are procedures also required? Does the design institute also need to produce the drawings? (I heard that technical upgrades aren’t necessary?) ) Thank you.
Reply #22018-03-10
1. Prepare the pipeline installation supervision and inspection report as well as the vessel quality certificate to go to the Quality Supervision Bureau to obtain the use registration certificate. 2. For pipelines, modifications, and major repairs, a notification usually needs to be submitted; for specific details, refer to the Safety Technical Supervision Regulations for Pressure Pipelines.
Reply #32018-03-10
This should be reported first by the unit responsible for the installation or modification.
Reply #42018-03-10
Thank you. Isn’t the Special Inspection Agency in charge of these things?
Reply #52018-03-10
Inspections by the Special Inspection Agency, as well as notifications and registrations, are all handled by the Quality Supervision Bureau
Reply #62018-03-10
1. In accordance with the requirements for the management of special equipment, the pressure pipelines and pressure vessels of newly installed systems must go through the process of obtaining a registration certificate from the local special equipment regulatory authority within 30 days after they come online. 2. For newly added pressure vessels and pressure pipelines, design changes are generally required by the original design unit; any modifications to pressure vessels must be reported to the local quality supervision department
Reply #72018-03-11
The pressure pipelines and pressure vessels of newly installed facilities must obtain the registration certificates from the local special equipment regulatory authority within 30 days after commissioning. For newly added pressure vessels and pressure pipelines, design changes should generally be carried out by the original design unit
Reply #82018-03-12
The construction unit must have the relevant qualifications and also complete the notification procedures.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.