The medium flowing in the pipeline is gas; is it necessary to install a drain at the lowest point of the pipeline? A hydrostatic test is required

2018-06-15View Original

Thread Content

I would like to ask everyone: the medium flowing through the pipeline is gas, with operating parameters of 130°C and 1.1 Mpag. Steam tracing is required, and a hydrostatic test shall be conducted on site. There is a low point in the pipeline route; is it necessary to install a drain at that low point?
Reply #22018-06-15
Want to add a valve or a flanged cover for draining water.
Reply #32018-06-16
How can the water accumulated in the lower areas after the hydrostatic test be drained without using a drain pipe?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.