The mating flanges are pre-installed on the equipment flanges; can the flanges and pipes be welded on-site without removing them?

2021-07-09View Original

Thread Content

There are flanges on the equipment; matching flanges are installed before leaving the factory, and these flanges are buttwelded flanges. Since disassembly affects the seal, can the flange not be removed on-site, and can the steel pipe be welded to the already installed flange? Is that okay? If possible, where are the relevant regulations? No, please let the expert also explain why.
Reply #22021-07-09
If you don’t remove the flange and weld directly, will the high temperature of welding affect the seal of the flange? It’s okay as long as it doesn’t cause any problems, right? I can’t think of any others for now
Reply #32021-07-09
American standard butt weld flanges, with a very high weld neck and thick thickness as well. It seems so too; the temperature must be high, but I don’t think it will be that extremely high
Reply #42021-07-09
Are there a lot of typos in your question? It’s a bit confusing to read
Reply #52021-07-09
First, check the temperature that the seal can withstand, and then ask the welding engineer about the expected temperature. Try to get a rough estimate first; also, consider whether post-weld heat treatment is necessary, as that will also result in high temperatures.
Reply #62021-07-09
It is possible as long as the seal is not affected
Reply #72021-07-09
Well, it seems so; basically, what it means is that the mating flanges allow the steel pipes to be welded after installation?
Reply #82021-07-09
Since it is for export, I’m not sure if there is any basis for this. Could you tell me which standard it is?
Reply #92021-07-09
First of all, thank you for your analysis. I’ll go check it. Rubber R01 for sealing.
Reply #102021-07-09
It seems that I really haven’t noticed any evidence for this
Reply #112021-07-10
Generally speaking, it would be better to weld the flanges on the pipelines first, and then install the equipment or valves, etc

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.