As the title suggests, are there any safety distance requirements between the fuel unloading point at a grade-3 gas station and the high-voltage lines outside the station?
Reply #22021-08-22
It seems there are requirements; for high-voltage lines, refer to the Regulations on the Protection of Electric Power Facilities
Reply #32021-08-31
\"Code for Gasoline, CNG, and Hydrogen Refueling Station Projects\" 2.1.10: The distance between the process equipment in gasoline, CNG, and hydrogen refueling stations and the overhead power lines and communication lines outside the station should be no less than 5 meters; The distance between the process equipment installed outdoors on the ground and the overhead power lines and communication lines outside the station should be no less than 1 times the height of the pole.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.