【Daily Question】【AC Version for Static Equipment...Question 168】June 17, 2019 Multiple-choice questions...Essay questions ........

2019-06-18View Original

Thread Content

bg4.png【Daily Question】【AC Version for Static Equipment...Question 168】June 17, 2019 Multiple-choice questions...Essay questions .....................................................Reward rules: 3 wealth for participation, 5–10 wealth for answers that are close to the correct ones. ...........................................................................What are the responsibilities of the pressure vessel design agency?.................................................................... Answer: ①Be responsible for the accuracy and completeness of the design documents ; ②The design documents should include at least calculations and drawings ; ③The design general plan is stamped with the qualification seal of the design unit.
Reply #22019-06-18
Responsible for the accuracy and completeness of the design documents; The design documents should include at least calculations and drawings ; The design general plan is stamped with the qualification seal of the design unit.
Reply #32019-06-18
①Responsible for the accuracy and completeness of the design documents; ②The design documents should include at least calculations and drawings ; ③The design general plan is stamped with the qualification seal of the design unit. (Section 3.2.2.1 of GB150-1998)
Reply #42019-06-18
1. The design unit shall be responsible for the accuracy and completeness of the design documents; 2. The design documents for the container shall include at least a design calculation sheet and design drawings ; 3. The general layout diagram of the container design shall bear the approval mark from the pressure vessel design unit.
Reply #52019-06-18
①Responsible for the accuracy and completeness of the design documents; ②The design documents should include at least calculations and drawings ; ③The design general plan is stamped with the qualification seal of the design unit.
Reply #62019-06-18
Derived from GBT150.1 a): The design unit is responsible for the correctness and completeness of the design documents; b) The design documents for the container shall include at least a strength calculation report, design drawings, manufacturing specifications, and a risk assessment report (when required by relevant regulations or the client who commissioned the design); if necessary, installation and operation/maintenance instructions shall also be included ; c) The general design drawing of pressure vessels falling within the scope of the \"Regulations on Safety Supervision of Fixed Pressure Vessels\" shall bear the seal for design approval of special equipment ; d) The risk assessment report issued by the design unit to the container user shall meet the requirements of Appendix F ; e) The design entity shall retain all container design documents throughout the design service life of the containers.
Reply #72019-06-18
1. The design unit shall be responsible for the accuracy and completeness of the design documents; 2. The design documents for the container shall include at least a design calculation sheet and design drawings ; 3. The general layout diagram of the container design shall bear the approval mark from the pressure vessel design unit.
Reply #82019-06-18
This post was last edited by wwguo on 2019-6-18 20:42; they are responsible for the accuracy and completeness of the design documents; The design documents should include at least calculations and drawings ; The design general plan is stamped with the qualification seal of the design unit.
Reply #92019-06-18
Responsible for the accuracy and completeness of the design documents; The design documents should include at least calculations and drawings ; The design general plan is stamped with the qualification seal of the design unit.
Reply #102019-06-18
Responsible for the accuracy and completeness of the design documents; The design documents should include at least calculations and drawings ; The design general plan is stamped with the qualification seal of the design unit.
Reply #112019-06-18
①Responsible for the accuracy and completeness of the design documents; ②The design documents should include at least calculations and drawings ; ③The design general plan is stamped with the qualification seal of the design unit. (Section 3.2.2.1 of GB150-1998)

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.