This post was last edited by chenjdvip on 2022-8-27 at 15:08. A equipment supervision company, commissioned by the owner, carried out phase-by-phase supervision of the equipment manufactured by a certain factory
Reply #22021-11-13
1. Is it illegal to manufacture the equipment at Location B? How should equipment supervision be corrected? It depends on whether the registered geological supervision authority issues a manufacturing inspection certificate for him. 2. Does the head factory need to issue an inspection certificate for the heads? I’ll just shape the melon slices for you; no certificate should be issued. 3. Does the final non-destructive testing report require the signature of the manufacturer? Needed
Reply #32021-11-15
Answer: 1. The supervisor should submit a deviation to the factory regarding manufacturing at Location B. Location B falls outside the scope of the pressure vessel manufacturing license issued by the manufacturing unit; therefore, a permit for off-site manufacturing of the project must be obtained from the provincial authorities. 2. Not necessary. 3. Required
Reply #42021-11-15
1. Site B is non-compliant for the following reason: the equipment manufacturing certificate does not include Site B, and container manufacturing processes related to regulatory requirements cannot be carried out at Site B. Site B should obtain its own certification or have its operations included in the certification for Site A. 2. The head factory does not carry out welding work, so it is not required to have supervision during inspection ; 3. Weld inspection is outsourced; the entrusted party must possess the appropriate qualifications, and the manufacturing plant must have a compliant outsourcing authorization letter ; A report is issued by the non-destructive testing service provider ; The manufacturer shall include the qualified test reports (with relevant information on any repairs made in the case of defective items) in the equipment quality certificate; no signature is required.
Reply #52021-11-16
This is the kind of problem that arises in EPC projects for pressure vessels
Reply #62021-11-16
Those who have worked on mobile factories know these requirements

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.