HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

Ball tank hydrostatic test

2023-09-05View Original

Thread Content

Hydraulic test of spherical tanks: I. After the installation of the spherical tank is completed, a pressure test and a airtightness test shall be carried out in accordance with the specifications provided in the drawings. II. During the pressure test, a pressure gauge with the same range and calibrated properly must be installed at both the top and bottom of the spherical tank. It is advisable to choose a pressure gauge with a range of about 2 times the test pressure, but it should not be less than 1.5 times or more than 3 times the test pressure. It is advisable that the diameter of the pressure gauge be no less than 150 mm. The test pressure is based on the reading of the pressure gauge at the top of the spherical tank. III. Before the pressure test, compressed air at a pressure of 0.4~0.5 MPa should be introduced into the opening reinforcement rings of the spheres and tanks to check the quality of the welds. IV. Hydrostatic Testing 1. Water is generally used for hydrostatic testing; other liquids that do not pose any risks can also be used if necessary. 2. The test pressure shall comply with the provisions of Article 3.11.2 of GB 12337-2014. 3. Test temperature: (1) The temperature of the liquid during testing should be below its flash point or boiling point. (2) When performing hydraulic testing on spherical tanks made of Q345R, Q370R, and 07MnMoVR, the liquid temperature must not be lower than 5℃ ; When conducting hydraulic tests on Q245R and other low-alloy steel spherical tanks, the liquid temperature must not be lower than 15°C. If factors such as plate thickness cause the material’s plastic transition temperature to increase, the testing temperature must be raised. 4. Test requirements: (1) An exhaust port should be provided at the top of the spherical tank during testing. The air inside the spherical tank must be exhausted when filling it. During the test, the outer surface of the spherical tank should be kept dry. (2) During the test, the pressure should be increased gradually; once it reaches 50% of the test pressure, it should be held at that level for 15 minutes. Afterward, a leak check should be conducted on all welds and connections of the spherical tank, and only after confirming no leaks are present should the pressure be increased further. (3) When the pressure rises to the design pressure, hold it for 10 minutes, then conduct another leak check; only after confirming no leaks are present should the pressure be increased further. (4) When the pressure rises to the test pressure, hold it for 30 minutes, then reduce the pressure to the design pressure and conduct an inspection; no leakage is considered acceptable. (5) After the hydraulic test is completed, the liquid should be drained, and the tank should be dried out using compressed air. During drainage, it is strictly prohibited to discharge it on site. 5. Requirements for foundation settlement; (1) During the process of filling and draining the spherical tank, the settlement of the foundation should be monitored at the following stages: before filling ; When the liquid level reaches 1/3 of the sphere shell diameter ; When the liquid level reaches 2/3 of the sphere shell diameter ; After 24 hours of being filled with liquid ; After draining the liquid. (2) The settlement of each pillar foundation should be measured, and the foundations of all pillars should settle evenly. After fluid drainage, the differential settlement of the foundation shall not exceed Db/1000 (where Db is the diameter of the base circle in mm), and the differential settlement between adjacent pillar foundations shall not exceed 2 mm. When exceeded, measures should be taken to address it.
Reply #22023-09-05
The hydraulic test of spherical tanks is a pressure and airtightness test conducted on such tanks. When conducting hydraulic tests, water or other liquids that do not pose a danger are commonly used. The test pressure and temperature must be adjusted in accordance with relevant regulations; in addition, exhaust vents must be provided, the outer surface of the spherical tank must be kept dry, and leak checks must be carried out. During the test, the pressure should be increased gradually; after maintaining it at a certain level for a while, a leak check is conducted, and finally the pressure is reduced to the design value for a final inspection. After the test is completed, the liquid must be drained, and the tank should be dried out using compressed air. Additionally, during the hydraulic test, it is also necessary to monitor and measure the settlement of the spherical tank foundation; the settlement should be uniform and not exceed the specified range, and measures must be taken if it does. .

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.