Progress in the construction of the second phase of Xinjiang Zhongneng Wanyuan project, which has an annual production capacity of 400,000 tons of synthetic ammonia and 600,000 tons of urea

2021-11-24View Original

Thread Content

Progress on the Phase II of the Xinjiang Zhongneng Wanyuan project, which aims to produce 400,000 tons of synthetic ammonia and 600,000 tons of urea per year. Author/Source: Sinochem 13th Construction Company. Date: November 24, 2021. Clicks: 22. To date, 6 large-scale pieces of equipment with a total weight of 1,300 tons have been installed at the Xinjiang Zhongneng Wanyuan project, and 70% of the installation work for the gasification unit has been completed. The project team is carrying out the preparation work for lifting the large-scale equipment of the gasification unit, namely the pulverized coal feed tank and the pulverized coal lockhopper.
Reply #22021-11-25
70% of the installation work for the entire gasification unit has been completed

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.