This post was last edited by yuchenchf on 2017-1-18 at 17:04. Reward for participation: 2 Wealth. Correct reward: 9 Wealth. A certain construction project uses a unit price contract; during the measurement of a specific work item, it is found that due to changes in the project requirements, the actual amount of work completed by the contractor exceeds the amount specified in the bill of quantities. Then, when measuring this work item ( ). A. Calculated based on the quantities specified in the tendered bill of quantities. B. Calculated based on the quantities of work completed by the contractor in fulfilling its contractual obligations. C. Calculated based on the quantities of work submitted by the contractor as completed. D. Calculated based on the quantities of work verified by the employer. B
B. Calculated based on the volume of work completed by the contractor in fulfilling its contractual obligations
A certain construction project used a unit price contract. During the measurement of a specific work item, it was found that due to project changes, the actual amount of work completed by the contractor exceeded the amount specified in the bill of quantities; therefore, when measuring that work item, ( B ). A. Calculated based on the quantities specified in the tendered bill of quantities. B. Calculated based on the quantities of work completed by the contractor in fulfilling its contractual obligations. C. Calculated based on the quantities of work submitted by the contractor as completed. D. Calculated based on the quantities of work verified by the employer
B. Calculated based on the volume of work completed by the contractor in fulfilling its contractual obligations