Participation reward: 2 Wealth. Correct reward: 9 wealth. A certain construction project was contracted under a fixed-unit-price agreement. The construction of the foundation works took 1 year, with an inflation rate of 8%. Upon completion, the actual volume of reinforced concrete work carried out was 2016 m3, while the volume specified in the bill of quantities at the time of bidding for this item was 2000 m3. Under such circumstances, the owner shall calculate the amount of payment due for this item based on (  ).   A. 2000 m3 multiplied by the contract price B. 2000 m3 multiplied by the adjusted price C. 2016 m3 multiplied by the contract price D. 2016 m3 multiplied by the adjusted price Reference: C
Reply #22017-01-16
C. 2016 m3 multiplied by the contract unit price
Reply #32017-01-16
C. 2016 m3 multiplied by the contract unit price. The characteristic of a unit-price contract is that the unit price takes precedence; the actual payment is calculated by multiplying the actual volume of work completed by the contract unit price to determine the amount due. Since a fixed-price contract is used, the correct answer is C.
Reply #42017-01-16
C. 2016 m3 multiplied by the contract unit price

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.