Participation reward: 2 Wealth. Correct reward: 9 wealth. According to the \"Code for Quantity Calculation of Construction Projects\" (GB 50500–2013), the damages and additional costs resulting from force majeure events shall be borne by the employer.   A. Damage to the project itself B. Injuries or deaths of personnel at the employer’s site C. Damage to the contractor’s construction machinery D. Costs associated with cleaning up the site E. Costs required for repairing the project Reference: A B D E
Reply #22017-01-16
A. Damage to the project itself B. Injuries or deaths of personnel at the employer’s site D. Costs associated with cleaning up the site E. Costs required for repairing the project
Reply #32017-01-16
C. Damage to the contractor’s construction machinery: According to the \"Code for Quantity Calculation of Construction Projects\" (GB 50500–2013), any damage or increased costs resulting from force majeure events shall be borne by the employer; this applies to (C. damage to the contractor’s construction machinery).

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.