【Piping Valve Technology Edition – Daily Question on Common Piping Errors】20170724

2017-07-24View Original

Thread Content

Discussion on Common Piping Errors 008: Which of the following designs (the diagram shows a piping design for a tower) is correct? A. B. Answer: B. When there is a large temperature difference between the pipeline and the tower wall, resulting in relative elongation, this elongation should be absorbed by the individual branches, and the length of L should be sufficient to accommodate such relative elongation. PS: Excerpted from the Chemical Pipeline Design Manual
Reply #22017-07-24
There are 2 piping designs; when the temperature difference between the tower wall and the piping is small, design A is acceptable. When the temperature difference between the tower wall and the piping is large, B is correct. Due to temperature differences, the thermal expansion and contraction of the pipes should be absorbed by the branch pipes, and their length L should be sufficient to accommodate the amount of compensation resulting from heat.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.