When will the equipment on the side walls of the prefabricated panel houses be installed?

2020-12-19View Original

Thread Content

The color panel features a hidden purlin design, with an inner panel, an intermediate insulation layer, and an outer panel. There are wall-mounted fans; the fan type is shown in the diagram. Should the fan be installed after the inner panels are in place, or after the outer panels are installed? What’s the reason? Thank you!
Reply #22020-12-20
Install the color panels and edge seal the holes
Reply #32020-12-24
Install it after all the panels have been installed; at the location where the equipment will be placed, you can use custom-made panels with pre-drilled holes

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.