HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

What are the inspection items and standards for accepting instrument equipment upon arrival?

2019-04-25View Original

Thread Content

Could some expert please share information on the inspection process for instrument equipment upon delivery? What aspects are checked, and are there any specific inspection standards? Thank you~~~
Reply #22019-04-26
Visual inspection, parts counting, trial assembly
Reply #32019-04-26
Upon the arrival of the equipment, an unpacking inspection is carried out jointly by the owner (preferably a relevant technician), the supplier, the construction party, the supervision company, and on-site representatives from the materials department. An external inspection is conducted to check the name, specifications, quantity, and condition of the equipment, with detailed records being kept. 1. Preparation work: shipping list, technical agreement (or supply contract), and identification of the personnel responsible for unpacking along with the necessary tools. 2. When opening the box, use appropriate tools; avoid harsh knocking or pounding to prevent damage to the equipment. Extra care should be taken to protect boxes that contain precision equipment. 3. Electrical and instrumentation equipment and accessories shall be inspected together with electrical and instrumentation professionals before being handed over to them for storage. 4. Thoroughly count and inspect spare parts supplied randomly, and store and use them properly. 5. If damage to the equipment is detected upon unboxing, or if quality defects are found during subsequent installation, it is necessary to promptly examine the situation together with the supplier’s representative and discuss appropriate actions to take. 6. The instruction manuals and related materials for the randomly assigned equipment should be properly kept for future installation and debugging purposes, and a record should be maintained. 7. The technical documents shall be verified in accordance with what is specified in the technical agreement; in particular, for imported equipment and accessories, customs declarations and certificates of origin (or certificates issued by local chambers of commerce) are required ; For easy archiving, the supplier is required to provide a bound volume of technical documents, along with a document index for reference.
Reply #42019-04-26
First, conduct a visual inspection; then check the accompanying documents (technical agreement, instruction manual, certificate of conformity), verify whether spare parts are provided, and finally keep an inventory record of the equipment. Something else is being dealt with during the installation phase

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.