Installation and fixation of the tray in the instrument cabinet

2021-03-05View Original

Thread Content

Can the support for the instrument trays inside the instrument cabinet be achieved by welding brackets to the steel structure of the cabinet? There are three trough boxes between the two rows of cabinets. I’m thinking of welding a continuous support shelf directly to the legs of the steel foundations of those cabinets – is that feasible? ? ? ? Will it affect the stability of the foundation?
Reply #22021-03-06
According to clause 6.2.7 of the interpretation of GB 50093-2013, welding shall not be used for the installation of instrument panels. This is because replacing or moving dashboards, boxes, and cabinets can pose difficulties in terms of welding methods; furthermore, since these dashboard, box, and cabinet components are usually made of sheet metal, welding can cause thermal deformation.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.