Progress on the resumption of construction of the Datang Fuxin coal-to-natural gas project

2018-04-19View Original

Thread Content

Progress on the Resumption of Construction of the Datang Fuxin Coal-to-Natural Gas Project Author/Source: Yaha Coal Chemical Industry Date: 2018-04-19 Clicks: 12 On the morning of April 18, Fuxin Coal-to-Natural Gas Company held a ceremony to kick off the construction of the waterproof flooring in its power center, marking the start of a new phase of project development. Yang Baojiang, the company’s deputy general manager, attended the groundbreaking ceremony. At the groundbreaking ceremony, Yang Baojiang expressed his gratitude to Sinopec Construction Company for its support in the construction of the Datang Fuxin project. He pointed out that the coal yard anti-seepage floor project is the second project to commence construction under the company this year. With the start of this project, the progress of the company’s overall projects will accelerate further. He hoped that the engineering department, the safety, construction, and environmental protection department, as well as the supervision company, would play their proper roles, organize work carefully, carry out construction in a scientific manner, and effectively speed up the project timeline while ensuring quality and safety. At the same time, it is hoped that the project team for the Power Center will persevere and go all out to advance the construction of the project. The representatives of the project participants also stated firmly that they would carry out the project construction to high quality and high standards, in accordance with the requirements of Fuxin Company, and were confident, determined, and capable of delivering a satisfactory project that features fast progress, excellent quality, and high standards! Project Overview: This project involves the construction of an anti-seepage floor for the coal storage area at Liaoning Datang International Fuxin Coal-to-Natural Gas Co., Ltd. The coal storage area is of the open-strip type, with a length of 645 meters and a width of 371 meters; the floor is made of reinforced concrete with anti-seepage properties, covering a total area of 212,410 square meters. On April 12, 2018, the construction work on the utility pipelines and evaporation crystallization facilities for the wastewater treatment system of the Datang Fuxin coal-to-natural gas project commenced. The launch of this project marks the official resumption of construction for the Fuxin coal-to-natural gas project.
Reply #22018-04-20
Thanks for sharing! ! ! ! ! ! ! !
Reply #32018-04-23
The Datang Fuxin coal-to-gas project has been in operation for almost 7 or 8 years now. Such a long construction period – this is typical of large state-owned enterprises; otherwise they would have collapsed long ago. It is hoped that with the resumption of work, construction can be completed and operations can begin by the scheduled time.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.