Participation reward: 2 Wealth. Correct reward: 6 wealth. Multiple-choice question: In an engineering network plan, the condition for identifying critical tasks is that such tasks ( ). A. The free float is minimum. B. The time interval between it and the task that follows it is zero. C. Its duration is the longest. D. The earliest start time is equal to the latest start time. D
Reply #22017-05-05
In engineering network planning, the condition for identifying a critical task is that task (D). A. The free float is minimum. B. The time interval between it and the task that follows it is zero. C. Its duration is the longest. D. The earliest start time is equal to the latest start time
Reply #32017-05-05
D. The earliest start time is equal to the latest start time. In a project network plan, the condition for identifying critical tasks is this task (D). A. The free float is minimum. B. The time interval between it and the task that follows it is zero. C. Its duration is the longest. D. The earliest start time is equal to the latest start time

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.