HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

Problems with unloading ethylene oxide storage tanks

2015-08-14View Original

Thread Content

This post was last edited by Desert Fish on 2015-8-14 09:16. There is a 10m3 ethylene oxide storage tank inside Category A equipment; the tank truck connects directly via hoses, and the nitrogen supplied by the truck is used to push the material into the tank. In that case, it should not be necessary to install a unloading platform, right?
Reply #22015-08-14
This way, there should be no need to set up a unloading platform
Reply #32015-08-14
This question helps you shift to the storage and transportation sector; I hope there can be more exchanges
Reply #42015-08-14
It seems there are no regulatory requirements. Is the work site located in an explosion hazard area? Can vehicles pass there?
Reply #52015-08-14
Vehicles can pass by, and a hard surface has been installed around the storage tank to withstand the load from tank trucks. If this isn’t considered a unloading platform, then I only need to consider the fire separation requirements between such outdoor equipment classified as Category A and the surrounding buildings; otherwise, I would also have to take into account the fire separation requirements for the unloading platform, and there isn’t enough space for that. . . How does everyone handle it?
Reply #62015-08-14
Both loading and unloading of ethylene oxide require an operating platform, as well as flexible hoses.
Reply #72015-08-14
The ethylene oxide tank truck approaches the liquefied gas tank truck, which has liquid-phase and gas-phase ports (with docking boxes on the side of the tank truck). No loading platform is required; a safety island should be installed (usually 200 mm high to prevent tank trucks from entering the equipment area). For operational safety reasons, a dip pipe should be used.
Reply #82015-08-14
This cannot be done; tank trucks cannot directly discharge contents into the storage tanks inside the device. A raw material tank must be installed, from which the material is then transferred to the intermediate tank of the device. .
Reply #92015-08-17
Which standard requires this? Thank you for your advice :)
Reply #102015-08-17
What this sea friend is saying is that I don’t need to design a unloading platform; I can directly transfer ethylene oxide from the tank truck into the plant’s storage tanks via the tank truck interface, so there’s no need to consider the spacing between unloading platforms either? Are there any projects similar to this?
Reply #112015-08-17
Is this really necessary? Are there corresponding specifications?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.