Can the detailed design be used for construction?

2015-08-20View Original

Thread Content

As the title suggests, can detailed design drawings replace construction drawings so that the construction party can carry out work according to them?
Reply #22015-08-20
1. Aren’t detailed design drawings construction drawings? 2. Even if you draw things in great detail, it may be only on a partial level and not meet the overall requirements; after all, the overall design plan has not yet been finalized, and changes to the plan could occur at any time, in which case it won’t be usable.
Reply #32015-08-20
Is the design process one of preliminary design, detailed design, and finally the production of construction drawings?
Reply #42015-08-20
This post was last edited by ylb913 on 2015-8-20 21:17. We call them preliminary design, basic design, and construction drawing design. 1. I have attended many preliminary design review meetings; these involve reviews by all the relevant professionals from the client side. After these reviews, the main details of the project are basically finalized, and many adjustments are made to the design during this process ; 2. It seems that not as many professionals are involved in the review phase after the basic design is completed; I’m not too sure about this since I haven’t attended any conferences. I have participated in the review of PIDs as a person from the process engineering field, and this involves some minor details related to the process itself, so it really shouldn’t take too much time ; 3. Two weeks before the construction drawings are finalized, we will conduct another review, which is also carried out by the process engineering team; its main purpose is to assess the rationality of the piping layout, and only after this review are the official construction drawings issued. After the equipment begins to be installed underground, there is often a process of coordination with the detailed design. In the past, our factory would request from the design institute detailed drawings of the fundamental structures and frameworks; this was done mainly to prepare the necessary materials in advance so as to meet the requirements of the construction schedule.
Reply #52015-08-21
It’s just 3 steps: basic design BD, detailed design DD, and as-built drawings AS-built; the detailed design enables on-site construction. Therefore, the detailed design can serve as construction drawings.
Reply #62015-08-21
Sure, the basic design, detailed design, preliminary design, and construction drawings can all be used as a basis for construction. With the approval stamp and pipe sealing stamp applied, there’s no need to worry about what the design specifies; just build according to the drawings.
Reply #72015-08-21
Isn’t detailed design nothing but construction drawings?
Reply #82015-08-21
Feasibility study – basic design – detailed design – as-built drawings; the detailed design can serve as the construction drawings
Reply #92015-08-21
The official detailed design drawings from the design institute are the blueprints with the approval stamp – they are definitely ready for construction!
Reply #102015-08-21
Detailed design is also known as construction drawing design.
Reply #112015-08-21
The detailed design is divided into versions E, F, and G; version G of the detailed design corresponds to the construction drawing design.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.