Everyone, take question 72-2015 from the First-Class Constructor Examination’s \"Project Management\" section – there is a reward for those who answer it correctly

2015-11-18View Original

Thread Content

Let’s work on question 72-2015 from the First-Class Constructor Examination’s \"Project Management\" section – there is a reward for those who answer it correctly. Those who do these questions every day are truly enthusiastic learners! ! Today marks the start of the project management series – welcome to join! http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png Some questions from this year’s first-level constructor exam have been collected, along with their answers. I’m sharing them here to encourage more people to participate. Instead of posting all the questions at once, a few multiple-choice questions or one case study will be presented each time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; those who give correct answers will receive rewards from the moderators. ****************************************** After completing the questions, it’s time to rest, and enjoying delicious food is the best way to do that. Everyone is encouraged to click on the posts related to food topics: a summary post of the “Food Search” series. Feel free to share your own ideas as well, and you’re also welcome to join discussions in the safety-related section. Fun posts about traffic violations – summary post********************* 58. Which of the following statements about the tracking of construction contracts is incorrect? ( ) A. The contract management department of the contracting unit is responsible for tracking, monitoring, and inspecting the performance of those who carry out the contract tasks. B. The parties responsible for carrying out the contract tasks themselves are in charge of tracking, checking, and comparing the progress against the contract plan. C. The content of contract tracking includes whether the client provides instructions and responses in a timely manner. D. The project tasks can be assigned to specialized subcontractors, who will then be responsible for tracking, checking, and comparing the progress against the contract plan. Answer: D
Reply #22015-11-18
D、--------------------------------------------------------
Reply #32015-11-18
58. Regarding the tracking of construction contracts, the incorrect statement is (d). D. Engineering tasks can be assigned to specialized subcontractors for completion, who are responsible for tracking, monitoring, and comparing the implementation of the contract plan
Reply #42015-11-18
D. Engineering tasks can be assigned to specialized subcontractors for completion, who are responsible for tracking, monitoring, and comparing the implementation of the contract plan
Reply #52015-11-18
58. Regarding the tracking of construction contracts, the incorrect statement is (D). A. The contract management department of the contracting unit is responsible for tracking, monitoring, and inspecting the performance of those who are responsible for executing the contract. B. Those who are responsible for executing the contract themselves are in charge of tracking, checking, and comparing the progress of contract implementation. C. The contents of contract tracking include whether the client provides timely instructions and responses. D. The project tasks can be assigned to specialized subcontractors, who will then be responsible for tracking, checking, and comparing the progress of contract implementation
Reply #62015-11-19
Regarding the statements on construction contract tracking, the incorrect one is (d)
Reply #72015-11-19
C. Contents of contract tracking and whether the owner provided instructions, responses, etc., in a timely manner
Reply #82015-12-06
D Establish a system quality control network

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.