Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. During the construction of a certain project, the contractor covered up a certain concealed area without notifying the supervisor for inspection. The supervisor instructed the contractor to uncover it for inspection, and upon inspection, it was found that the quality of that concealed area met the requirements specified in the contract. According to the Standard Construction Bidding Documents, the additional costs and/or schedule delays incurred this time shall be borne by ( ). A. Employer B. Supervisor C. Contractor D. Subcontractor 【Production and Management Division】Seeking moderators and technical discussants to join
Reply #22015-12-01
The additional costs and/or delays in schedule shall be borne by (C, the Contractor).
Reply #32015-12-01
C. Contractor. -------------------
Reply #42015-12-01
The operating time of inverse-time overcurrent protection is set according to a stepped principle, with the time interval generally taken as (C × 0.7S).
Reply #52015-12-01
During the construction of a certain project, the contractor covered up a certain concealed area without notifying the supervisor for inspection. The supervisor instructed the contractor to uncover it for inspection, and upon inspection, it was found that the quality of that concealed area met the requirements specified in the contract. According to the Standard Construction Bidding Documents, the additional costs and/or delays in schedule shall be borne by (C, the Contractor).
Reply #62015-12-01
During the construction of a certain project, the contractor covered up a certain concealed area without notifying the supervisor for inspection. The supervisor instructed the contractor to uncover it for inspection, and upon inspection, it was found that the quality of that concealed area met the requirements specified in the contract. According to the Standard Construction Bidding Documents, the additional costs and/or delays in schedule shall be borne by (C).
Reply #72015-12-01
During the construction of a certain project, the contractor covered up a certain concealed area without notifying the supervisor for inspection. The supervisor instructed the contractor to uncover it for inspection, and upon inspection, it was found that the quality of that concealed area met the requirements specified in the contract. According to the Standard Construction Bidding Documents, the additional costs and/or delays in schedule shall be borne by (C). A. Employer B. Supervisor C. Contractor D. Subcontractor
Reply #82015-12-01
My answer: C...............................

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.