Pipe explosion occurred during the pressure testing of high-pressure steam pipes in the power plant

2016-08-12View Original

Thread Content

What are people’s opinions on the pipe explosion that occurred during the pressure testing of the high-pressure steam pipes at Dangyang Thermal Power Plant? Why didn’t the safety valve activate?
Reply #22016-08-12
During the pressure testing process, the safety valve should be isolated; what’s the truth behind explosions in power plant steam pipes?
Reply #32016-08-12
So the safety valve doesn’t protect the pipeline; does that mean the pipeline fails and bursts even without overpressure?
Reply #42016-08-12
If a pressure test is conducted, the explosive force is not that great, and such situations generally do not occur in steam pipelines. I think it might be due to water accumulation in the pipeline, which wasn’t thoroughly blown out, resulting in instant vaporization. A leak in a high-pressure steam pipe only produces a large amount of mist. But the identification results depend on the **experts. I just hope they don’t choke on the contents of their stomachs.
Reply #52016-08-12
But the pipeline is first drained of water before steam is introduced; it’s rather abnormal that the safety valve does not activate
Reply #62016-08-12
A hydrostatic test wouldn’t have such power
Reply #72016-08-12
Seek the truth – were no issues detected during the pressure test?
Reply #82016-08-13
Will a hyperpressure test be carried out? The steam temperature is 600 degrees, and the control room is completely destroyed – it’s terrifying
Reply #92016-08-15
It is very unlikely that a valve will function fine during pressure testing but will develop serious problems in actual operation. This accident revealed problems with the design of the control room; it was located within a hazardous explosion zone and lacked explosion-proof measures. This design must date back to the early 1990s, as the design firm failed to update such drawings in accordance with current standards. In the past, the main steam pipes in our company’s boiler section passed through the windows of the control room, but that setup was removed several years ago. It is hoped that the design institute will develop a intrinsically safe device to deliver to the owner, and that it will also make proper use of Hazop analysis in the design process.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.