Domestic sulfur-based compound fertilizer projects are already quite mature; let’s discuss this: Is it better to install the drying kilns in the compound fertilizer production facility before the roof is completed, or after it is completed? For the sulfur-based compound fertilizer production facility, is it better to install the cooling machine before the roof of the facility is completed, or after it is completed?
Both the dryer and the cooler are large and long devices; it is recommended to lift them into place before the factory roof is completed.
Generally, the equipment foundation is built first, and then the large-scale equipment is lifted into place. Wait until the factory building is completed and the equipment has been installed, then proceed with debugging. Not to mention reaching the ceiling – it’s best even to avoid working on the nearby columns and foundations for now, as lifting operations will cause interference. :)
There are now vertical dust-free coolers that take up less space than traditional horizontal kilns, and are also easier to install
It seems you’re quite familiar with this area. Are you from an installation company?
Vertical dust-free coolers are indeed good, but if humidity and air flow aren’t properly controlled, it’s easy for blockages and scabs to form; Moreover, vertical dust-free coolers require a lift to operate, need water cooling, which increases the investment cost.
Vertical coolers require corresponding process design, but they are extremely effective. I was the first company in China to use this type of equipment for compound fertilizers; feel free to ask me if you have any questions