This post was last edited by Clouds of flowing water shine on 2017-11-7 at 09:13. The attached photo shows the installation site of the pump outlet pipe; due to time constraints, the quality of the photo is not very good. Please analyze whether there are any issues with the installation of the pump outlet pipe
This post was last edited by Clouds of flowing water shine on 2017-11-13 11:24. Why can’t I upload attachments? Both the image and the area around it show that it has been uploaded, but the result cannot be seen. Image 3m
This post was last edited by Clouds of flowing water shine on 2017-11-14 11:13. How do you upload pictures?
This post was last edited by Clouds of flowing water shine on 2017-11-20 09:18. An upload error 500 occurred; after using a screenshot, the file size became 300k and it was possible to upload it.
If I were the one to do the installation, I wouldn’t design it this way; I would have the outlet pipelines of the two pumps connected to the manifold separately.
It’s a matter of angle regarding the connection of the outlet pipeline to the manifold; in fact, it’s not connected. The outlet pipelines of the two pumps are combined into a single main pipe that leads to the absorption tower.
The two pumps should not operate at the same time.
What I’m actually referring to is the installation direction of the two valve actuators, as well as the installation direction of the pressure gauge. Do you think this arrangement is satisfactory?
There are also nuts on the bolts; some are on top and some are on the bottom. Which one is correct?