Container venting and pipeline sealed discharge

2019-01-30View Original

Thread Content

Everyone, I have a question: for CBD and HBD systems, the main discharge pipes are located at the top of the pipe tray. Why is it required that the valve assemblies on these pipes be placed at the lowest point, with the elevation increasing only after the valves? I’m a beginner; I hope everyone will be kind enough to offer some guidance.
Reply #22019-01-30
The light blue tube was originally on the platform, but the reviewer requested it be placed below
Reply #32019-01-31
It seems to be about the requirements for operation and maintenance; installation on the ground improves both operability and maintainability

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.