How many blueprints are generally required for the manufacturing equipment of pressure vessel manufacturers?

2018-05-23View Original

Thread Content

Previously, our company had several pieces of equipment that were manufactured by a machinery factory; we gave them three sets of blueprints. Later, they said that those weren’t enough and asked for more. How many sets of blueprints are generally needed in such situations? I think three sets should be sufficient – one set for the workers in the factory who carry out the manufacturing, and two sets as part of the documentation required for delivery. Are there any other requirements?
Reply #22018-05-23
Three are needed for just one unit. For multiple units (n), the number of blueprint sheets is equal to n multiplied by 2 plus 1
Reply #32018-05-23
The number varies among manufacturers, but generally there are 6 sets: one for the technical department, one for the process department, one for the materials department, one for quality control, one for the workshop, and one for archiving. (See the arrangements of various company departments)
Reply #42018-05-23
Three sets will be enough; if it’s not enough, let them print it out themselves, otherwise we’ll end up with as many copies as mentioned above
Reply #52018-05-23
One set is required for inspection, and the documents to be provided include two sets of as-built drawings per unit (one set for departure from the factory and one set for archiving). In accordance with regulatory requirements, design documents must also be supplied (including design drawings, calculation sheets, etc.). Therefore, at least four sets of drawings are needed per product, and copies can be used for production purposes.
Reply #62018-05-23
It no longer matters whether they are blueprints or engineering copy drawings, but at least two sets of drawings bearing the design seal for pressure vessels must be available. The rest can be copied; as for who does the copying, it’s according to the agreement.
Reply #72018-07-22
Per unit, at least 5 sheets per unit, at least 7 sheets for 2 units, and so on
Reply #82018-07-22
For large companies, even more are required; for example, one unit needs 6–7 sheets, and two units need 8–9 sheets each
Reply #92018-07-22
Of course, only the set kept by the technical department and the two sets used for inspection purposes need to be stamped with the red seal; the others can be copied
Reply #102018-07-22
The required quantity is: 1 set for the workshop, 1 set for the manufacturing process, 1 set for archiving, plus the number of delivery documents needed by the customer. This represents the minimum requirement
Reply #112019-10-28
Hello, you mentioned that at least two sets of drawings stamped with the pressure vessel seal are required. Why are two sets needed?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.