How to arrange the shock absorption grooves on the compressor testing platform

2018-03-05View Original

Thread Content

The foundation of the compressor testing platform is reinforced using powder jetting piles; the compressor generates vibrations during operation, so shock-absorbing ditches are installed around it. What are the requirements for the layout of these shock-absorbing ditches, and which field is responsible for handling this task? Is it the architectural field?
Reply #22018-03-05
The piping department provides the compressor vibration frequency and the total weight of the machine. There are civil engineering calculations for foundations.
Reply #32018-03-06
Thank you. How should it be arranged? Should a trench be dug around the compressor platform? Can cables be placed in that trench?
Reply #42018-03-06
How to do it requires consideration by civil engineering professionals.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.