What meetings must a project manager for an automation project (such as a DCS-related project) attend throughout a project?

2017-02-14View Original

Thread Content

What external meetings do project managers need to attend? Who are the other parties attending, and what topics need to be determined? Thank you, hero~
Reply #22017-02-21
Clarification meeting on the supplier’s technical proposal; A project kickoff meeting is held once the supplier is selected, covering the responsible party and date for document delivery, the software implementation plan, factory testing, etc ; During the construction phase, coordinate the placement of cabinets, power-up, and testing in line with the project’s installation progress ;

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.