Are there any standard regulations regarding the order and time intervals for producing drawings by different specialties in design institutes?

2022-12-21View Original

Thread Content

Are there any regulations specifying the sequence and time intervals for various specialties in a design institute to produce construction drawings? Now the management requires that all specialties produce their drawings together. According to standard project practices, the instrumentation specialty is supposed to complete its drawings within one month after the piping specialty has done so. Is there any basis for this requirement?
Reply #22022-12-21
A specific order for producing drawings is necessary, but the time interval between them is not fixed; this depends on the volume of design work and the human resources allocated to it.
Reply #32022-12-21
“The leader requested that all departments collaborate to produce the drawings.” This requirement is easy to meet; the design institute can wait until all the design drawings from various departments have been stored before producing the final drawings and conducting another design briefing.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.