HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

High-level discussions on the construction of the DMTO unit as part of the project to address deficiencies in the Shaanxi Yanchang China National Coal Group Yulin Energy and Chemical Industry complex

2019-07-24View Original

Thread Content

High-level meeting held on the construction of the DMTO unit for the completion project of Phase 1 of Shaanxi Yanchang China Coal Yulin Energy Chemical Co., Ltd.’s project – Author/Source: Huahua Network Coal Chemicals; Date: July 24, 2019; Clicks: 2. On July 20, a high-level meeting was held regarding the construction of the DMTO unit (intermediate tank area) as part of the completion project for Phase 1 of this company’s project. Li Wei, General Manager of Yulin Energy Chemical Company, emphasized in his speech that all parties must focus on completing the three key tasks of \"ground management, steel structure construction, and ground hardening\" by the end of August, in order to create the conditions necessary for the \"installation campaign\" in September. The results of this campaign will be crucial for achieving the goals set for March 30th. On the other hand, in light of the current delays in the construction of DMTO facilities and the existing practical problems, the senior management of both parties attaches great importance to these issues; they have held several coordination meetings and developed a timeline for progress. Luoyang Engineering Company must make full use of the \"golden period\" for construction in the second half of the year, meet the set requirements, fulfill the plans, and ensure the successful achievement of the goals set by CCCC. Zhou Chengping, general manager of Sinopec Luoyang Engineering Company, said that the goal of completing the DMTO unit by March 30 is unshakable. To ensure the successful achievement of this goal, Luoyang Engineering Company will formulate a practical implementation plan by the end of July and adhere strictly to it ; Furthermore, it is essential to ensure the proper arrival of equipment and materials, to promptly replenish on-site management personnel and construction workers, and to make every effort to advance the project schedule. At around 10 a.m. on July 20, the oil-immersed transformer of the 35 kV utility substation for the Yulin Energy Chemicals filling and completion project was officially lifted, marking the beginning of the installation of electrical equipment in the utility substation. It is understood that this is the first oil-transformer unit to be lifted for the filling and completion project. It is reported that there are two oil-immersed transformers to be lifted this time, each weighing 22 tons. They represent one of the core components of utility substations, and once installed, they will supply power to areas such as the desalination station, the fourth circulating water facility, and the air separation unit as part of the completion and improvement projects. A responsible official from the Electrical and Instrumentation Center said that next, procurement will be carried out for the remaining part of the 10 kV casting busbars, and installation work on the medium and low voltage switchgear cabinets will begin. The Electrical and Instrumentation Center will go all out to complete the installation of electrical equipment in the utility substation to the required standard and quality, thereby creating favorable conditions for the ignition of the boiler at the thermal power station as part of the completion projects on September 30. As of the end of June, 2.71 billion yuan had been invested in the completion and supplementation works for the first phase of the project undertaken by Shaanxi Yanchang China Coal Yulin Energy Chemical Co., Ltd. (the Yanchang Jingbian Phase II project); 645 million yuan was invested in June alone, and the construction of various facilities is progressing steadily. The completion and improvement project for the first phase of Shaanxi Yanchang China National Coal Group Yulin Energy Chemical Co., Ltd. (Yanchang Jingbian Phase II project) is a key project aimed at implementing the directives of the Shaanxi Provincial Party Committee and the provincial government to \"enhance the demonstration effect of the comprehensive utilization projects for coal, oil, and gas resources in Jingbian\", as well as the requirements of Yanchang Petroleum Group to \"change its business model and adjust its structure\". With an investment of 14.413 billion yuan, this project will use coal and natural gas as raw materials to build an integrated facility capable of producing 1.8 million tons per year of methanol, 600,000 tons per year of methanol-to-olefins products, 400,000 tons per year of polypropylene, and 300,000 tons per year of low-density polyethylene/Ethylene-Vinyl Acetate copolymer (LDPE/EVA).
Reply #22019-07-24
Quarterly coordination meetings are held to summarize the progress achieved in the first half of the year and to outline the construction plans for the second half.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.