What is the “three simultaneities” system?
“The \"three simultaneities\" system refers to a requirement that for all new construction, renovation, and expansion projects, as well as technical transformation projects and natural development projects, as well as other engineering construction projects that may cause pollution and damage to the environment, the facilities for preventing pollution and other environmental hazards, along with other environmental protection facilities, must be designed, constructed, and put into use simultaneously with the main project itself.
“The \"three simultaneities\" system refers to a requirement that for all new construction, renovation, and expansion projects, as well as technical transformation projects and natural development projects, as well as other engineering construction projects that may cause pollution and damage to the environment, the facilities for preventing pollution and other environmental hazards, along with other environmental protection facilities, must be designed, constructed, and put into use simultaneously with the main project itself.
Environmental protection or safety facilities must be designed, constructed, and put into use simultaneously with the main project
Designed, constructed, and put into use simultaneously.
According to Article 41 of China’s Environmental Protection Law, which came into effect on January 1, 2015, \"Facilities for pollution control in construction projects shall be designed, constructed, and put into use simultaneously with the main project itself.\" Facilities for pollution control shall comply with the requirements of the approved environmental impact assessment documents, and shall not be removed or left idle without authorization. "
“The \"three simultaneities\" system refers to a requirement that for all new construction, renovation, and expansion projects, as well as technical transformation projects and natural development projects, as well as other engineering construction projects that may cause pollution and damage to the environment, the facilities for preventing pollution and other environmental hazards, along with other environmental protection facilities, must be designed, constructed, and put into use simultaneously with the main project itself.
Design, construct, and put into use simultaneously
The safety facilities for new construction, renovation, or expansion projects of such production and operation units must be designed, constructed, and put into use simultaneously with the main structure of the project.
Construct simultaneously, build at the same time, conduct inspections and put into use at the same time
Design simultaneously, construct simultaneously, put into production simultaneously