[Haichuan Chemical News] Zhejiang Petrochemical’s 4,000-ton crane completed the installation of the continuous reforming reactor

2018-10-22View Original

Thread Content

The 4,000-ton class crawler cranes were used for the first time in the 40 million tons per year integrated refining and chemical processing project of Zhejiang Petrochemical. Crawler Crane Resource Sharing Platform, 0927, 17:57. The No. 1 unit of the first phase of Zhejiang Petrochemical Co., Ltd.’s 40 million tons per year integrated refining and chemical processing project – the 380 million tons per year continuous reforming unit – features “three-in-one” and “two-in-one” reforming reactors. With a height of 96 meters and a weight of 613 tons each, these are China’s largest reforming reactors to date. At Zhejiang Petrochemical’s 40 million tons per year integrated refining and chemical processing project in Zhoushan, the lifting of the reforming triple-reactor was completed as part of the lifting integration contract awarded to Sinopec Transportation Company; this marked the first construction task carried out by that company after taking over such a large-scale piece of equipment. This set of reforming reactors consists of reduction sections/reforming reactors 1, 2, and 3, namely 2 \"three-in-one\" reactors, and buffer zones/reforming reactors 4 and 5, namely 2 \"two-in-one\" reactors. The \"three-in-one\" reactors are as tall as 96 meters and weigh 613 tons each; they represent China’s largest reforming reactors to date, setting a new record for Lansi’s reactor manufacturing and marking a milestone in this field.
Reply #22018-10-22
Even heavy equipment is a piece of cake for a giant crane: lol
Reply #32018-10-22
Is this long, slender device the reforming reactor? If it weren’t specified, I would definitely think it’s a distillation tower
Reply #42018-10-22
A reforming reactor, seeing one for the first time.
Reply #52018-10-22
A high lifting position is a challenge.
Reply #62018-10-22
The skirt base is in the middle and needs to be placed inside the frame; since it’s a concrete frame and there are large cranes available, none of these pose any problems
Reply #72018-10-22
It might be due to the larger scale and different installation method; the skirt base has been moved to the middle
Reply #82018-10-22
It might be due to the larger scale and different installation method; the skirt base has been moved to the middle

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.