I can’t remember where I saw it, in a specification or a catalog. It is said that plastering should be carried out 45 days after the masonry is completed. Please **provide the specific standard number or catalog number! ! !
Reply #22015-07-01
This is a construction issue; I’m not very familiar with it. Generally, it should be possible once the mortar used for wall construction has reached its strength
Reply #32018-10-19
Generally, plastering can be carried out 7 days after the masonry work is completed (including the installation of the top sloping bricks), and once the main structure has passed the inspection. According to the specifications, it is 45 days later.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.