Participation reward: 2 Wealth. Reward for correct answer: 9 Wealth. Multiple-choice question: Regarding the location where construction joints in concrete should be placed, which of the following is correct? ( ) A. Beams with a height greater than 1m should not have their concrete poured simultaneously with that of the slabs. B. One-way slabs can be placed at any position parallel to the shorter side. C. Construction joints in concrete walls must not be located at the junctions of vertical and horizontal walls. D. Construction joints in concrete balustrades should correspond to those in the stair treads
Regarding the location where concrete construction joints should be placed, the correct options are (ABD). A. Beams with a height greater than 1m should not have their concrete poured simultaneously with that of the slabs. B. One-way slabs can be placed at any position parallel to the shorter side. C. Construction joints in concrete walls must not be located at the junctions of vertical and horizontal walls. D. Construction joints in concrete balustrades should correspond to those in the stair treads
A. Beams with a height greater than 1m should not have their concrete poured simultaneously with that of the slabs. B. One-way slabs can be placed at any position parallel to the shorter side. D. The construction joints of concrete balustrades should correspond to those of the stair treads
Regarding the location where concrete construction joints should be placed, the correct options are (A, B, C).