Regarding the issue of adding manual valves and blind flanges to the pipeline leading to the flare separator tank

2016-08-13View Original

Thread Content

That expert knows whether it is reasonable to install manual valves and blind flanges on the pipelines leading to the torch separator tank; if so, what precautions need to be taken. Are there any relevant provisions in that standard as well?
Reply #22016-08-13
There’s no particular principle behind this; under normal conditions, a flare tower does not contain much liquid. If there is a problem, it’s not a big issue to shut it off for a short period of time. To address this, options include installing inlet and outlet valves as well as a bypass line, or simply adding an inlet valve for the liquid phase at the lowest point of the flare line.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.