Participation reward: 2 Wealth. Reward for the correct answer: 9 wealth. The time quota for a certain construction machine is 0.2 machine-days per 100 m3; if the worker team working with it consists of 4 people, then the output quota for this machine is ( ) m3 per machine-day.   A.5.0 B.500  C.1.25 D.125 Correct answer: B
Reply #22016-08-29
If the time quota for a certain construction machine is 0.2 machine-days per 100 m3, and the worker team working with it consists of 4 people, then the output quota for this machine is (C) m3 per machine-day.   A.5.0 B.500   C.1.25 D.125

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.