I need help regarding the responsibility for setting the safety valve on the module. .

2016-09-28View Original

Thread Content

I would like to ask all fellow sailors: is it the manufacturer who applies to have the safety valve on the module calibrated by the local pressure vessel inspection agency, or is it the installation crew who goes to that agency to carry out the calibration when the module is installed? ? ? Who is generally responsible for this? . .
Reply #22016-09-29
What do you mean by module? Complete set of equipment? If it is a complete set of equipment, it has already been calibrated before leaving the factory
Reply #32016-09-29
It’s a relatively complex module. . It includes net equipment, process pipelines, electrical instruments, etc. Can this be classified as complete equipment?
Reply #42016-09-29
It depends on how you place the order; if it falls within the manufacturer’s supply range, then everything can be finalized

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.