Notice of Commencement of Work

2016-11-29View Original

Thread Content

How many copies are needed for the boiler commissioning notification, and who should they be given to?
Reply #22016-11-29
It should be four copies: one for the county-level boiler inspection agency, one for the city-level boiler inspection agency, one for the user, and one for oneself
Reply #32016-11-30
Download a notice; there are instructions below, and four copies are required. However, what was said above isn’t entirely accurate; at the county level, there are usually no inspection agencies for pots, so in practice, one copy is given to the notifying unit and another to the supervising inspection unit.
Reply #42016-11-30
Generally, there are four copies: one is kept by the installation unit, one is handed over to the owner upon completion, and the other two are stored and given to whoever needs them.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.