Is it necessary to install a vent valve at the high point of the tube side piping in a heat exchanger?

2017-03-24View Original

Thread Content

The shell side of the reboiler at the bottom of the tower is heated with hot water. Is it necessary to install a vent valve at the highest point of the shell side pipes? Are there any design specifications?
Reply #22017-03-24
It’s optional, but it’s better to include it for emptying at higher levels
Reply #32017-03-24
What I do is to add it, so as to facilitate pressure testing and emptying
Reply #42017-03-24
Not necessarily; it depends on the actual situation. When adding something, ease of use needs to be taken into consideration.
Reply #52017-03-24
Air resistance will slow down your startup process; it’s better to add it.
Reply #62017-03-25
It’s optional; decide based on the actual conditions on site

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.