Latest progress on the Yushen ethanol project

2021-07-30View Original

Thread Content

Latest Progress of the Yushen Ethanol Project Author/Source: Shaanxi Yanchang Petroleum Yulin Coal Chemical Co., Ltd. Date: 2021-07-30 Clicks: 4 Since the beginning of this year, Yushen Energy & Chemical Company has focused on further refining tasks, raising standards, and accelerating work efforts to push forward the construction of the 500,000 tons per year coal-based ethanol project, and good results have been achieved in this project’s development. To date, the overall progress of the Yushen 500,000 tons per year coal-based ethanol project has reached 67.98%. The main tasks related to the detailed design of all facilities in the plant have been completed; procurement is approximately 81.79% finished, and construction is about 55.48% complete, of which civil work is around 73.40% done and installation work is about 19.93% complete.
Reply #22021-07-30
The overall progress is 67.98% complete; it seems there’s an issue with this weight

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.