HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

Everyone, take question 63-2: multiple-choice questions 45-46 from the 2015 First-Class Constructor Examination in Project Management; there will be a reward for those who answer correctly

2015-11-14View Original

Thread Content

This post was last edited by Desert Fish on 2015-11-14 08:01. Everyone, please work on question 63-2: the multiple-choice questions 45-46 from the 2015 First-Class Constructor Examination in Project Management. There will be a reward for those who answer them correctly. Those who do these exercises every day are truly enthusiastic learners! ! Today marks the start of the project management series – welcome to join! http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png Some questions from this year’s first-level constructor exam have been collected, along with their answers. I’m sharing them here to encourage more people to participate. Instead of posting all the questions at once, a few multiple-choice questions or one case study will be presented each time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; those who give correct answers will receive rewards from the moderators. ****************************************** After completing the questions, it’s time to rest. Everyone is encouraged to click on the posts in the food category: a compilation of posts related to food searches. Feel free to share your own ideas. 45. During the inspection of a construction project, it was found that the quality of the exterior wall tiles was unsatisfactory. Upon investigation, it turned out that the problem stemmed from the quality of the materials supplied by the vendor. The project team decided to switch to another vendor. This measure falls under which category of project objective control? A. Management measures B. Organizational measures C. Economic measures D. Technical measures. Correct answer: B. 46. For large-scale construction projects carried out using the design-build contract model, with a construction period of three years, what is the typical contract pricing method used? A. Fixed-price contract B. Unit-price contract C. Cost-plus contract D. Variable-price contract. Correct answer: D
Reply #22015-11-14
During the construction inspection of a certain project, it was found that the quality of the exterior wall tiles was substandard. Upon investigation, it was determined that the problem stemmed from defects in the materials supplied by the vendor. The project team decided to switch to another supplier; this measure falls under the (b) organizational measures for project goal control
Reply #32015-11-14
For large-scale construction projects implemented under the EPC model, with a construction period of three years, the contract pricing method generally adopted is (d) D variable total price contract
Reply #42015-11-14
45 During the construction inspection of a certain project, it was found that the quality of the exterior wall tiles was substandard. Upon investigation, it was determined that the problem stemmed from defects in the materials supplied by the vendor. The project team decided to switch to another supplier. This measure falls under (B) of project objective control: A. Management measures; B. Organizational measures; C. Economic measures; D. Technical measures. 46 For large-scale construction projects carried out using the design-build contract model, with a construction period of three years, the typical contract pricing method used is (D): A. Fixed-price contract; B. Unit-price contract; C. Cost-plus contract; D. Variable-price contract
Reply #52015-11-14
45 B Organizational measures 46 D Variable total price contract
Reply #62015-11-14
Worth learning* – it broadens your horizons and will be useful in the future
Reply #72015-11-15
Group B: Organizational measures; Group C: Cost-plus contract

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.