【Joint Study*】【Civil Engineering Version 20160131】

2016-02-01View Original

Thread Content

Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. Among the following statements, which one does not conform to the provisions of the Construction Law regarding contract work? ( ) A. Construction companies are prohibited from undertaking projects beyond the scope of work permitted by their respective qualification levels. B. Construction companies are prohibited from undertaking projects in any manner under the name of other construction companies. C. It is prohibited for two or more contracting units to jointly undertake construction projects. D. It is prohibited to divide a project and assign it in separate parts
Reply #22016-02-02
Among the following statements, the one that does not comply with the provisions of the Construction Law regarding contract work is (C). A. Construction enterprises are prohibited from undertaking projects beyond the scope of business permitted by their respective qualification levels. B. Construction enterprises are prohibited from undertaking projects in any form under the name of other construction enterprises. C. It is prohibited for two or more contracting units to jointly undertake construction projects. D. It is prohibited to divide projects and assign them separately
Reply #32016-02-02
Among the following statements, the one that does not comply with the provisions of the Construction Law regarding contract work is (C). A. Construction enterprises are prohibited from undertaking projects beyond the scope of business permitted by their respective qualification levels. B. Construction enterprises are prohibited from undertaking projects in any form under the name of other construction enterprises. C. It is prohibited for two or more contracting units to jointly undertake construction projects. D. It is prohibited to divide projects and assign them separately
Reply #42016-02-02
Among the following statements, the one that does not conform to the provisions of the Construction Law regarding project contracting is (C). A. Construction enterprises are prohibited from undertaking projects beyond the scope of business permitted by their respective qualification levels. B. Construction enterprises are prohibited from undertaking projects in any form under the name of other construction enterprises. C. It is prohibited for two or more contracting units to jointly undertake construction projects. D. It is prohibited to divide projects and assign them separately
Reply #52016-02-02
C. It is prohibited for two or more contracting entities to jointly undertake construction projects
Reply #62016-02-02
Among the following statements, the one that does not comply with the provisions of the Construction Law regarding contract work is (C). A. Construction companies are prohibited from undertaking projects beyond the scope of work permitted by their respective qualification levels. B. Construction companies are prohibited from undertaking projects in any manner under the name of other construction companies. C. It is prohibited for two or more contracting units to jointly undertake construction projects. D. It is prohibited to divide a project and assign it in separate parts
Reply #72016-02-02
Among the following statements, the one that does not comply with the provisions of the Construction Law regarding contract work is (C). A. Construction companies are prohibited from undertaking projects beyond the scope of work permitted by their respective qualification levels. B. Construction companies are prohibited from undertaking projects in any manner under the name of other construction companies. C. It is prohibited for two or more contracting units to jointly undertake construction projects. D. It is prohibited to divide a project and assign it in separate parts

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.