Start-up and shutdown times of catalytic cracking units

2016-05-30View Original

Thread Content

Regarding the scheduling of startup and shutdown periods for catalytic cracking units, why is it 3 days of shutdown followed by 4 days of operation? What are the specific requirements? Thank you! ! !
Reply #22016-05-30
There’s no fixed requirement for this; it depends on the actual conditions of the device. If a large amount of lining needs to be replaced, it will take several days just to heat up the dryer, and production will also have to stop. The decision depends on factors such as the specific temperature.
Reply #32016-05-30
Operation must be carried out in accordance with the heating curve; this time period cannot be skipped, especially when replacing the lining in large quantities!

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.