CV priority order in APC

2017-09-14View Original

Thread Content

I would like to ask: in APC advanced control, how is the priority order of the controlled variables determined? Is it based on process requirements? For example, in the vapor-phase propane removal column, the CV priority order is reflux drum level > top temperature = bottom temperature > reflux feed ratio. How is such an order determined?
Reply #22017-09-14
Most of the people here are involved in maintenance; APCs with advanced control functions are generally out of reach for ordinary people.
Reply #32017-09-14
It’s so core. Generally, it is confirmed during the final briefing in the technical room; if there are no drawings available, you can proceed according to the process requirements first
Reply #42017-09-15
Generally, it is in accordance with the process control requirements; however, I have never seen the liquid level in the reflux tank being set as Cv
Reply #52017-09-15
It would be convenient to know which company’s APC software is being used

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.