After the furnace bricks of the gasifier are installed, bake the furnace for a few days

2018-10-19View Original

Thread Content

May I ask, if only the barrel bricks of the gasification furnace are replaced, how long does it take to let it air dry before heating it up? How many days does it take to bake the furnace? If replacing the entire set of bricks, how long should they be left to dry before firing? How many days does it take to bake the furnace? What about when changing the arch tiles? Thank you
Reply #22018-10-19
Generally, natural drying takes 72 hours; the time required to replace all the furnace bricks and bake the furnace is also around 72 hours. Most refractory brick manufacturers provide corresponding baking curves, though there may be slight differences

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.